Detours

Upcoming Construction that will impacted LBT service

8/14/2018 ~ 10/2018 – Redondo Ave @ Anaheim Southbound and Anaheim @ Redondo Ave Westbound
Major street repairs that will impact routes 45, 46 and 131. More information to follow.

Possible intermittent detours & bus stop closures for Routes 111 & 112

Update: 9/10/2018: Phase I Part A & B, Phase II Part A completed.
Buses are running regular schedule until further notice.

View detour details >

Broadway between Alamitos Ave. and Redondo Ave.
East and West.
To be completed in 4 phases.

Routes: 111 & 112
Effective: Wednesday July 11, 2018 until TBD
Hours: Entire Span of service

All American Construction Company has completed Phase II Part A and will begin Phase II Part B today Spetember 14, 2018. Beginning September 19, 2018 there will be a complete lane closure of the Eastbound lane on Broadway between Gaviota Ave / Lindero Ave.
View detour >

Phase I Part A
· Scheduled start date ~ 06/11/18
· Westbound between Alamitos Ave. / Gaviota Ave.
· Complete lane closure of Westbound traffic

COMPLETED – Reopened for now

Phase I Part B
· Scheduled start date ~ 07/09/18
· Eastbound between Alamitos Ave. / Gaviota Ave
· Complete lane closure of Eastbound traffic

COMPLETED – Reopened for now

Phase II Part A
· Scheduled start ~ 08.14.2018
· Westbound between Gaviota Ave. / Lindero Ave.
· Complete lane closure of the Westbound traffic

Completed – Reopened for now

Phase II Part B
· Scheduled ~ 09.19.2018
· Eastbound between Gaviota Ave / Lindero Ave.
· Complete lane closure of Eastbound traffic starting September 19, 2018

Active 09/14/2018

Phase III Part A
· Scheduled start date ~ TBD (will update)
· Westbound between Junipero Ave. / Redondo Ave.
· Lane closure TBD

Phase III Part B
· Schedule start date ~ TBD
· Eastbound between Junipero Ave. / Redondo Ave.
· Lane closure TBD